The rain has come right on time as we enter what is hopefully the final week of installation. The famous stump that we found at the base of the weir has been removed finally and last Friday the slab which will sit below the inlet screen was cast. The screen is set to go in place towards the end of the week – then we can remove the temporary dam and the installation will be physically complete. Our turbine ought to see its first flows for commissioning purposes sometime next week – if that goes well we hope to harvest a little of this rain perhaps even before October is out.