We have now finished the work widening and strengthening the tailrace, which will be taking a greater flow than it does now. Work on site will stop for a while, until mid-December. This is so that we do not impede or disturb the salmon run – work in the tailrace area was permitted, but the next stage will see us working at the weir to install the new sluices and the turbine itself.
-